Oracle 1Z0-129 certification exam has become a very influential exam which can test computer skills.The certification of Oracle certified engineers can help you to find a better job, so that you can easily become the IT white-collar worker,and get fat salary.
However, how can pass the Oracle 1Z0-129 certification exam simple and smoothly? DumpLeader can help you solve this problem at any time.
DumpLeader is a site which providing materials of International IT Certification. DumpLeader can provide you with the best and latest exam resources.The training questions of Oracle certification provided by DumpLeader are studied by the experienced IT experts who based on past exams. The hit rate of the questions is reached 99.9%, so it can help you pass the exam absolutely. Select DumpLeader, then you can prepare for your Oracle 1Z0-129 exam at ease.
In order to facilitate candidates' learning, our IT experts have organized the 1Z0-129 exam questions and answers into exquisite PDF format. Before your purchase, you can try to download our demo of the 1Z0-129 exam questions and answers first. You will find that it is almost the same with the real 1Z0-129 exam. How it can be so precise? It is because that our IT specialists developed the material based on the candidates who have successfully passed the 1Z0-129 exam. And we are checking that whether the 1Z0-129 exam material is updated every day.
The 1Z0-129 study materials of DumpLeader aim at helping the candidates to strengthen their knowledge about Oracle Primavera. As long as you earnestly study the 1Z0-129 certification exam materials which provided by our experts, you can pass the Oracle Primavera 1Z0-129 exam easily. In addition, we are also committed to one year of free updates and a full refund if you failed the exam.
Perhaps many people do not know what the Testing Engine is, in fact, it is a software that simulate the real exams' scenarios. It is installed on the Windows operating system, and running on the Java environment. You can use it any time to test your own 1Z0-129 simulation test scores. It boosts your confidence for 1Z0-129 real exam, and will help you remember the 1Z0-129 real exam's questions and answers that you will take part in.
The 1Z0-129 VCE Testing Engine developed by DumpLeader is different from the PDF format, but the content is the same. Both can be used as you like. Both of them can help you quickly master the knowledge about the Oracle Primavera certification exam, and will help you pass the 1Z0-129 real exam easily.
Oracle Primavera 1Z0-129 training materials contains the latest real exam questions and answers. It has a very comprehensive coverage of the exam knowledge, and is your best assistant to prepare for the exam. You only need to spend 20 to 30 hours to remember the exam content that we provided.
DumpLeader is the best choice for you, and also is the best protection to pass the Oracle 1Z0-129 certification exam.
All the customers who purchased the Oracle 1Z0-129 exam questions and answers will get the service of one year of free updates. We will make sure that your material always keep up to date. If the material has been updated, our website system will automatically send a message to inform you. With our exam questions and answers, if you still did not pass the exam, then as long as you provide us with the scan of authorized test centers (Prometric or VUE) transcript, we will full refund after the confirmation. We absolutely guarantee that you will have no losses.
Easy and convenient way to buy: Just two steps to complete your purchase, then we will send the product to your mailbox fast, and you only need to download the e-mail attachments.
Oracle 1Z0-129 Exam Syllabus Topics:
| Section | Weight | Objectives |
|---|---|---|
| Project Creation and Structure | 15% | - Define activities, activity codes, and calendars - Establish project hierarchy and relationships - Create new projects and configure project settings - Develop Work Breakdown Structure (WBS) |
| Cost Management | 10% | - Define cost accounts, expense categories, and cost types - Assign costs and expenses to activities and resources - Calculate and analyze project costs, budgets, and variances |
| Resource and Role Management | 15% | - Perform resource leveling and analyze allocation - Define resources, roles, and resource calendars - Assign resources and roles to activities - Manage resource curves and availability |
| Baseline and Progress Management | 10% | - Create and maintain baselines - Update project progress, actuals, and remaining work - Analyze performance and compare against baseline - Use timesheets and progress entry methods |
| Risk and Issue Management | 5% | - Log and resolve issues and changes - Identify, assess, and mitigate risks |
| Overview and Navigation | 10% | - Navigate user interface, menus, and views - Understand P6 EPPM architecture and components - Set user preferences and application settings |
| Customization and Administration | 5% | - Customize views, layouts, and reports - Manage security, users, and global data definitions |
| Scheduling and Logic | 20% | - Define activity relationships and constraints - Apply advanced scheduling techniques and lead/lag values - Perform scheduling calculations and analyze critical path - Understand duration types, percent complete types, and calculation methods |
| Portfolio and Program Management | 10% | - Create and manage portfolios and programs - Manage multiple projects and cross-project relationships - Use dashboards, reports, and portfolio analysis |
Oracle Primavera P6 2021 Enterprise Project Portfolio Management Sample Questions:
1. You are coaching a new Primavera Project Manager that is attempting to add a WBS Child element in their new project plan. The are in an Activity Table. The WBS icon is not available to this user.
What could be the problem?
A) They are not listed as the Project Manager for the project
B) They do not have security to add WBS elements
C) They have not selected the parent WBS element
D) They are not the Primary Resource for the Activity
2. Cost Variance is calculated as .
A) the Actual Cost of Work Performed
B) the Budgeted Cost of Work Scheduled
C) Budget at Completion - Earned Value Cost
D) Earned Value Cost - Actual Cost
3. An activity has an Original Duration of 10, and a Remaining Duration of 10. The Actual Start is assigned to the activity. Physical % is updated to equal 80%.What is the Remaining Duration for this activity?
A) 10
B) 8
C) 80
D) 2
4. You are in the dashboard section of Primavera P6 EPPM, in the Web interface. You would like data in the dashboard for one specific project. How would you make this happen?
A) Go to the "filter by" option and select the project.
B) Go to the Client and open the project.
C) Go to the Projects section and open the project
D) Go to the Portfolio section and filter by the project.
5. Select the true statement regarding the ability to create projects.
A) Any Project Manager can create a project.
B) Any Admin Super user can create a project.
C) Any Responsible Manager can create a project.
D) Any user can create a project
Solutions:
| Question # 1 Answer: D | Question # 2 Answer: D | Question # 3 Answer: B | Question # 4 Answer: C | Question # 5 Answer: C |







PDF Version
651 Customer Reviews
Quality and ValueDumpLeader Practice Exams are written to the highest standards of technical accuracy, using only certified subject matter experts and published authors for development - no all study materials.
Tested and ApprovedWe are committed to the process of vendor and third party approvals. We believe professionals and executives alike deserve the confidence of quality coverage these authorizations provide.
Easy to PassIf you prepare for the exams using our DumpLeader testing engine, It is easy to succeed for all certifications in the first attempt. You don't have to deal with all dumps or any free torrent / rapidshare all stuff.
Try Before BuyDumpLeader offers free demo of each product. You can check out the interface, question quality and usability of our practice exams before you decide to buy.